Construction of the massive, new William Beaumont Army Medical Center complex at Fort Bliss is almost two years behind schedule and at least $22 million over the original contract award.
The $648 million contracted construction cost of the six-building hospital complex has swelled to about $670 million, and will likely grow, Brad Hartell, the U.S. Army Corps of Engineers’ construction manager for the project, said during a recent tour of the construction site.